黑料社

Construction Tenders

01 April 2026

Related Information

Construction Contract Leads

East Midlands

Category Works

Type Tender

No. of Lots 1

Status Active

Published 30th Mar 2026

Tender Details
Referenceocds-h6vhtk-067831
Common Procurement VocabularyInstallation of cable laying
Procurement MethodCompetitive flexible procedure
Value£80,000,000
« Previous Page

East Midlands

Category Works

Type Tender

No. of Lots 1

Status Active

Published 30th Mar 2026

Tender Details
Referenceocds-h6vhtk-067831
Common Procurement VocabularyInstallation of cable laying
Procurement MethodCompetitive flexible procedure
Value£80,000,000

Scope

Reference

WS5607093027

Description

The successful framework contractor will be required to carry out the full installation of 66kV, 132kV and/or lower voltage cable circuits and associated earth wires / continuity conductors and NGED Telecom ducts inclusive of all jointing, testing and commissioning as specified for the individual route/project being tendered for.

Commercial tool

Establishes an open framework

A series of frameworks with substantially the same terms. Awarded suppliers are carried over and new suppliers can bid.

Total value (estimated)

  • 拢80,000,000 excluding VAT
  • 拢96,000,000 including VAT

Above the relevant threshold

Contract dates (estimated)

  • 29 May 2026 to 28 May 2027
  • Possible extension to 28 May 2028
  • 2 years

Description of possible extension:

Extension up to 12 months.

Main procurement category

Works

CPV classifications

  • 45314310 - Installation of cable laying

Contract locations

  • UKF - East Midlands (England)
  • UKG - West Midlands (England)
  • UKK - South West (England)
  • UKL - Wales

Framework

Open framework scheme end date (estimated)

29 May 2028

Maximum number of suppliers

Unlimited

Maximum percentage fee charged to suppliers

0%

Framework operation description

Full installation of 66kV, 132kV and/or lower voltage cable circuits and associated earth wires/continuity conductors and NGED Telecom ducts inclusive of all jointing, testing and commissioning as specified for the individual route/project being tendered for. All works will be in accordance with NGED policies and procedures.

All bonding systems shall comply with Electricity Network Association (ENA) Engineering Recommendation C.55/4.

All ducts used shall be as specified in NGED Policy and Procedures.

Testing & commissioning of the cable circuits shall be as specified in NGED Policy and Procedures.

The successful Contractor may be required to carry out design works as part of an installation contract, or as a separate instruction as required. This may be in the form of 'Cable System Design' or 'Cable Route Design'. Details of design requirements shall be specified for the individual route/project being tendered for.

Design work should take into consideration the best method of Ducting/Cable install work via Open Cut or Cable Ploughing methods dependant on Project-by-Project requirement.

The cable type, route length and any constraints / limitations will be specified for the individual route being tendered for.

The cable specification will be issued on a job-by-job basis

The route details shall be as specified for the individual route being tendered for. A detailed route survey may or may not be supplied at the invitation to tender stage.

Along the cable route there could be various 'Special Engineering Difficulties' (SED's) as specified on the individual route being tendered for. The tenderer is to allow for crossing all the SED's along the cable route with proposed methodology, including the install via HDD and designs for any shallow installs proposed to overcome SED's.

Allowance shall be made in programme for 3rd party agreement of crossing respective SEDs shall be as specified, unless alternatively specified by the cable manufacturer or on a project by project basis.

The successful contractor may be required to carry out decommissioning works. This shall be specified for the individual route/project being tendered for. All decommissioning works shall be as specified in NGED Policy and Procedures (NGED ST: CA9)

The contractor may be required to install telecommunication ducts and chambers. This shall be as specified in NGED Policy and Procedures.

The successful contractor will be fully responsible for liaising and co-ordinating with the relevant Highway Authority and the NGED "Streetworks" team with regards to all opening notice applications, traffic management requirements, parking restrictions, road closures, permit schemes etc. Opening notices and permit applications will be submitted by the contractor via the NGED "Streetworks" team.

The contractor will be responsible for the full resolution of all NRSWA defects, Section 74 fines and any other NRSWA issues associated with their works.

The successful contractor shall be responsible for liaison & consultation with all key stakeholders, including but not limited to the local Highway Authorities, private landowners, local residents (including neighbourhood groups), local schools, local businesses, bus companies, etc throughout the project. This may involve out of hours meetings/presentations and publicity publications.

The successful contractor shall also be responsible for notifying the above in writing giving sufficient notice of the works commencement with relevant out of hours contact details.

The Contractor should include a programme of the proposed works as part of his tender submission for each individual project. This should clearly break out key activities and milestones for the project and be submitted in a PDF and Microsoft Project format.

For confirmation the Client will require a contract programme to be developed and submitted by the successful Contractor following the Contract Award for each individual project for the acceptance of NGEDs nominated person. The programme will need to be updated and maintained on a monthly basis and shall indicate the critical path and the impact of all agreed variations to the programme. The programme is to be provided in PDF and Microsoft Project format.

The Contractor should include a payment profile against a proposed Programme of Works. The successful Contractor should submit Applications for Payments against the profile in a timely manner.

National Grid Electricity Distribution will either supply free issue materials for projects, or require the contractors to provide as part of their tender offer - the decision to be at NGED's discretion. Any free issue materials will be clearly specified under the heading 'Free Issue Materials' on a project by project basis. All other materials necessary for the full installation, jointing, testing commissioning, decommissioning or completion of the project scope of works, not identified under the heading 'Free Issue Materials' are to be allowed for and supplied by the contractor.

All free issue materials will be delivered to the successful contractors secure store/site.

The contractor will be required to co-ordinate the delivery of the free issue materials with the supplier as part of the requirements of the works. The contractor must therefore confirm with the supplier as soon as possible, the required section lengths, quantities etc.

Any materials not supplied by NGED must be in compliance with the requirements of the New Roads and Street Works Act 1991 and specification for the Reinstatement of Openings in Highways (HAUC) 1992.

The contractor shall be responsible for inspecting all NGED 'free issue materials' for quality and suitability in adequate time for rectification.

Storage and site office: The contractor will need to propose and secure a suitable site/s from which to carry out the works.

The Contractor should indicate the hours and days of the week they expect their staff to carry out the works in his response to each individual invitation to tender. This resource plan should include but not be limited to gangs and management staff and indicate the percentage of each week that they will be working on each individual project. This plan should align with the programme submitted in the tender for that project and be updated in line with the monthly programme.

The successful contractor shall allow provision for a secure location to store the all materials. Suitable and appropriate security shall be allowed for by the contractor to ensure the security of all materials whilst stored at this location and at remote work sites during the installation of all materials/cable and accessories. Suitable and appropriate security shall also be provided by the contractor to ensure the security of NGED's network while it is at risk from open excavations or reduced security as a result of the works. Until the time it is energised it will be the responsibility of the successful contactor and security provisions and insurance should be allowed for.

For all 66kV, 132kV and lower voltages cable routes, copper pilots and NGED Telecom duct route installations, the Contractor will produce a set of CAD as-built records, plus 2 sets of paper copies, based on the relevant Ordnance Survey maps, and 1 set of electronic copies, of the aforementioned records, in pdf format, of 'As Built' line diagrams drawn to ENATS 09-02 standard. These drawings will be ready for hand- over to NGED no more than 4 weeks after the cable has been laid.

The cable route records shall be developed as the duct laying proceeds. Interim submissions to the NGED records team, shall be made to allow the NGED records team to be preparing the route as the duct laying proceeds to reduce the work load at the end.

The rates are deemed to include for complying with the requirements of the New Roads and Street Works Act 1991 and the latest edition of the Code of Practice 'The Specification for the Reinstatement of Openings in Highways'. (The Specification).

The rates are also deemed to include for complying with the 'Traffic Management Act 2004' and all associated secondary legislation and codes of practice.

Road types are as defined by the Highway Authority. The road types encountered will be specified on the individual road summary sheet(s) provided on a project-by-project basis.

Recording the works will be, as laid down in the latest edition of National Grid Electricity Distribution, 'Basic Recording Techniques and Procedures'.

The Contractor is to provide an 'all-in rate' for the complete works.

Road types are defined above.

All Excavation, Cable Laying and Reinstatement Works shall be in accordance with Standard Technique CA6A.

The definitions of footways and verges are as those set out in HAUC specifications.

The rates shall include for all costs in connection with protecting the works.

The rates shall include for all costs in connection with bringing to, maintaining on and removing from site all plant necessary for the permanent and temporary work.

(Full details of the scope can be viewed once Expression of Interest to Participate is confirmed).

Award method when using the framework

Either with or without competition

Contracting authorities that may use the framework

Establishing party only


Submission

Enquiry deadline

30 April 2026, 5:00pm

Submission type

Requests to participate

Deadline for requests to participate

30 April 2026, 5:00pm

Submission address and any special instructions

To be submitted via National Grid's Ariba eSourcing platform. Full details of how to participate will be shared once National Grid receive requests to participate.

Tenders may be submitted electronically

No

Languages that may be used for submission

English

Award decision date (estimated)

29 May 2026


Award criteria

Name Type Weighting
Technical Quality 70%
Commercial Price 30%

Other information

Conflicts assessment prepared/revised

Yes


Procedure

Procedure type

Competitive flexible procedure

Special regime

Utilities

Competitive flexible procedure description

1. Declare interest to Participate

2. Receipt of Tender Documentation (via Ariba)

3. Return of Tender Documentation (via Ariba)

4. Evaluation of initial submissions

5. Negotiation (if required)

6. Tender Award (following Standstill period)


Documents

Documents to be provided after the tender notice

The Tender Pack will be provided on our e鈥憈endering platform (Ariba)


Contracting authority

NATIONAL GRID UK LIMITED

  • Companies House: 04508773
  • Public Procurement Organisation Number: PGTR-4481-CJPQ

1-3 Strand

London

WC2N 5EH

United Kingdom

Contact name: Janette McElroy

Telephone: +447872032616

Email: Janette.McElroy [at] nationalgrid.com

Region: UKI32 - Westminster

Organisation type: Private utility